Yes - a program-sized floor job needs a project quotation, not a catalog price. As an indicative worked example, a 10,000 m2 epoxy removal program consumes roughly 250-300 pieces of tooling across the strip pass, cleanup pass and edges. At that volume, unit prices typically drop 10-20 percent versus a 50-piece order, factories agree to split shipments matched to your schedule and price holds of 60-90 days, and lead times run about 25-40 days after sample approval.
Large projects fail on tool math, not tool price. Work backwards from the area:
| Job phase | Tool | Indicative life per set | Sets needed for 10,000 m2 |
|---|---|---|---|
| Strip 1-2 mm epoxy (open floor) | 2-3 PCD trapezoid disc, 6 pcs/set | ~700 m2 per set | ~15 sets (90 pcs) |
| Cleanup and profiling pass | 30/40# metal-bond disc, 6 pcs/set | ~450 m2 per set | ~22 sets (130 pcs) |
| Edges, columns, doorways (~4% of area) | PCD cup wheel, 125 mm | ~350 m2 per wheel | ~10 wheels |
| Buffer against breakage and reorders | 10% of total tool list | - | +25-30 pcs |
Total indicative tool list: about 250-280 pieces for a 10,000 m2 program. Scale the numbers to your own area, then add the factory recommended buffer. Two details move this math: thicker epoxy (over 2 mm) cuts PCD life by 20-30 percent, so order a bigger strip-pass buffer, and abrasive hard trowelled concrete shortens the cleanup discs, not the PCD shoes. Ask the factory to check your area, coating thickness and machine size against these typical wear figures before they lock the list.
A 10,000 m2 program burns tools over 6-10 weeks - you do not want the whole container delivered on day one. Ask for split shipments: a first small-lot or air-freight delivery to start the strip pass, then sea shipments timed to each project phase. This ties up less capital, keeps the job moving and avoids the emergency air-freight bill when stock runs dry mid-program.
Send the factory a sample of the proposed tool first - a WerkMaster-style PCD (JOY-WM-PCD1S1) for chip-style removal and an EDCO PCD plate (JOY-ED-PCD1) for the round-plate machine - and run it on 20 m2 before approving the program price.
A: Add sample approval (1-2 weeks) plus production (3-5 weeks) plus sea freight (3-6 weeks depending on destination). For a 10,000 m2 program, start the RFQ about 10-12 weeks before mobilization.
A: Yes - on project quantities, a 60-90 day price hold is standard, and annual programs usually lock pricing for the whole year.
A: Recurring program buyers commonly negotiate staged payments or LC terms; first orders typically follow the 30/70 deposit and balance structure.
A: PCD and metal-bond tooling has no expiry - plan the buffer into the next project. Ask the factory to keep your approved specification on file so reorders match the first batch.
A large epoxy removal job is priced by the program, not the piece: convert the floor area into a tool list, use tiered pricing to push the unit cost down, split shipments to your schedule, and lock terms in writing. Start with samples, confirm the specification with JOY TECH, and the factory will build the program price around your machine list, coating thickness and delivery calendar.